Tshepong

  FY14 FY13 FY12
Number of employees      
– Permanent 4 132 4 758 4 887
– Contractors 216 258 205
Total 4 348 5 016 5 092
Operational      
Volumes milled (000t) 947 1 040 1 233
Gold produced (kg) 4 223 4 154 5 287
Gold produced (oz) 135 772 133 554 169 980
Grade (g/t) 4.46 3.99 4.29
Productivity (g/TEC) 84.33 72.80 93.56
Development results      
Total metres (excl. capital metres) 12 762 13 125 15 159
Reef metres 2 209 2 541 2 237
Capital metres 79 352 570
Financial      
Revenue (Rm) 1 822 1 887 2 219
Average gold price received (R/kg) 433 425 456 294 421 643
Production profit/(loss) (Rm) 457 460 943
Capital expenditure (Rm) 301 310 288
Cash operating cost (R/kg) 326 498 343 895 243 087
All-in sustaining cost (R/kg) 415 061 441 108 312 106
Safety      
No of fatalities 2 1 2
Lost-time injury frequency rate per million hours worked 8.33 8.67 12.54
Environmental      
Electricity consumption (GWh) 301 310 298
Water consumption – primary activities (ML) 1 090 1 088 9 199
greenhouse gas emissions (000t CO2e) 299 307 295
Intensity data per tonne treated      
– energy 0.32 0.30 0.24
– water 1.15 1.05 7.46
– greenhouse gas emissions 0.32 0.30 0.24
Number of reportable environmental incidents 1 1 1
Community      
Local economic development (Rm)* 30 9 5
Training and development (Rm) 24.1 22.7 24

* Included in the total for FY14 is an amount of R22 million that was capitalised as part of the hostel upgrades

Both mill throughput and gold produced declined year-on-year, despite the increase in the grade recovered. Production from the decline project and mining of the B reef helped to stabilise production. More consistent performance is expected from Tshepong at current production levels in FY15. Delivery and commissioning of the fourth refrigeration plant contributed to improved working conditions. As the year progressed, the mine’s focus remained on increasing the number of stope faces in the higher-grade areas and maintaining reef development. Development of the major decline project continued within budget although there were delays following flooding in the decline, with steps being taken to prevent this in future. Construction of the 75 level continued. The chairlift to this level is expected to be commissioned in FY15.