Doornkop, which is situated 30 kilometres west of Johannesburg in the province of Gauteng, is a joint venture with BEE company African Vanguard Resources (Pty) Ltd, which has a 26% share in the mine.
Doornkop comprises a single shaft system of intermediate depth (maximum depth of 1 973m) and is serviced by the Doornkop carbon-in-pulp (CIP) Gold Plant.
At Doornkop, both the Kimberley and South reefs are mined by means of narrow reef, conventional mining and mechanised bord and pillar mining. Production at the Doornkop South Reef Project, on which development began in FY03 and which enables access to the higher grade South Reef, began in FY08. The project is currently being rampedup, with full production scheduled for FY15.
In FY09, Doornkop employs 2 532 people – 1 876 employees and 656 contractors.
At the end of June 2009, Doornkop reported ore reserves of 0.223 million ounces and mineral resources of 21.044 million ounces. Doornkop currently has an expected life-of-mine of 15 years.
The mine’s geological model on the South Reef continued to be improved as new information from delineation drilling and development became available. Additional exploration drilling will be undertaken in FY10 to increase the rate of gaining geological information on the South Reef orebody. Drilling platforms are being developed to enable exploration drilling to take place and to access the South Reef orebody in addition to normal access development. The objective of the additional exploration drilling is to reduce the risk of unknown geology and to improve the confidence levels of resources. See the mineral resources and ore reserves section (PDF - 82KB) for more detail.
Doornkop | Mineral resources | Ore reserves | |||||
Measured | Indicated | Inferred | Total | Proven | Probable | Total | |
---|---|---|---|---|---|---|---|
Oz (000) | 1 073 | 839 | 19 132 | 21 044 | 70 | 153 | 223 |
Tonnes (Mt) | 9.7 | 8.1 | 182.2 | 200.0 | 0.7 | 1.2 | 1.9 |
Grade (G/t) | 3.43 | 3.23 | 3.27 | 3.27 | 3.55 | 3.85 | 3.75 |
Doornkop’s safety performance continued to improve during the year, with the mine recording 16 months without a fatal accident. There were no fatal accidents at the mine in FY09 (FY08: one), while the LTIFR improved to 6.25 per million hours worked in FY09, from 8.55 in FY08.
Unit | FY09 | FY08 | FY07 | |
---|---|---|---|---|
Production | ||||
Volumes milled | 000 t (metric) | 549 | 448 | 541 |
000 t (imperial) | 605 | 494 | 597 | |
Gold produced | kg | 1 311 | 1 370 | 1 767 |
oz | 42 150 | 44 038 | 56 810 | |
Average grade | g/t | 2.388 | 3.06 | 3.27 |
oz/t | 0.070 | 0.089 | 0.095 | |
Financial | ||||
Revenue | R million | 343 | 258 | 263 |
US$ million | 38 | 35 | 37 | |
Cash costs | R/kg | 232 699 | 175 178 | 101 312 |
US$/oz | 804 | 749 | 438 | |
Cash operating profit | R million | 62 | 191 | 82 |
US$ million | 7 | 4 | 12 | |
Capital expenditure | R million | 395 | 349 | 270 |
US$ million | 44 | 48 | 38 |
Although performance at Doornkop improved year-on-year, FY09 was nonetheless disappointing as the operation reported ongoing under-performance against its plan. Production from the trackless mining sections on the Kimberley reef (76 and 106 levels) continued, but did not achieve the planned grade and volumes due to lower face grades and lower than normal trackless vehicle availability. Geological faulting on 192 level affected production build-up rates on the South Reef, as did the delays in the hoisting and water handling infrastructure capacity development. The latter was the main reason for the under-performance on the South Reef development and stoping objectives. Level 197 of the South Reef Project came into production in the second half of the year, boosting production from the project by more the 2009 quarter.
Despite the disappointing performance, volumes mined rose to 549 000 tonnes as the South Reef Project continued to ramp up.
The stoping plan is being built up to closely follow the development plan, with attention clearly being focussed on this critical factor. Development was much improved during the year with 97 729 metres achieved in FY09, on time and in line with plans.
The overall grade at Doornkop declined to 2.38g/t (FY08: 3.06g/t), mainly as a result of the decline in the grade mined on the Kimberley Reef and dilution of the South Reef ore. The delivered and recovered grade from the South Reef Project was negatively affected by dilution caused by the development waste rock that had to be tipped into the shaft reef system as a result of a delay in the commissioning of the waste rock handling system. The waste rock handling system was brought into operation during May 2009. The South Reef face grade is in line with expectations of 7.9 g/t.
The total amount of gold produced by Doornkop was 1 311 kilograms (42 150 ounces), 4% lower than production in FY08. Cash costs increased by 33% to R232 699/kg (US$804/oz) as a result of electricity tariff increases, higher labour costs and higher consumable store costs. A cash operating profit of R62 million (US$7 million) was reported at year-end.
Capital expenditure of R395 million (US$44 million) for the year was 13% higher than the previous year.
Trackless mining of the Kimberley Reef will continue for another two years while the build-up of production from the South Reef Project continues. Tonnes mined are expected to be in the region of 640 000 tonnes in FY10, at a recovered grade of 3.0 g/t. Cash costs** are anticipated to improve to approximately R172 000/kg (US$693/oz) in FY10.
Planned capital expenditure** for FY10 is R283 million (US$37 million) – R62 million ($8 million) on on-going development, R12 million (US$1.55 million) on other shaft capital and major equipment maintenance and R209 million (US$27 million) on the South Reef project.
* Please refer to the forward-looking statements (PDF - 54KB)
** June 2009 money terms. The exchange rate as at 30 June 2009 of R7.72/US$ has been used for all forward-looking conversions.
Following the start of production on this project in FY08, the build-up in volumes was slower in FY09 than had been planned, largely a result of logistical constraints and delays related to the transport of men and material, as well as the hoisting of ore. Production build-up resulted in increased pressure on available shaft time, which in turn led to delays in shaft construction work.
Major milestones during the year included the commissioning of the dual purpose winder and the dedicated winder to 132 level for mid-shaft loading from the Kimberley Reef section. In both May and June 2009, the operation achieved record monthly hoisting volumes and metres of development. South Reef development improved by 24% and stoping by 33% in the fourth quarter.
First production | July 2007 |
Full production | March 2015 |
Average annual production at full capacity | 776 kg; 250 000 oz |
Capital expenditure | R1.74 billion (US$186.5 million at R9.33/US$) R1.25 billion spent to date |
Expected life-of-mine | 15 years, to 2024 |
Average reserve head grade | 4.28 g/t |
Life-of-mine ounces | 2.72 million |